Challenge
At Moderna, the client set the challenge of saving 17 weeks on the overall construction, commissioning, qualification and validation (CQV) programmes. By establishing an on-site equipment testing facility, the team were able to provide a 10-week saving against the critical path. This included the fit out of a Drug Substance Facility, including associated manufacturing, cleaning, administration/office, warehouse, laboratory and hydronic/hygienic utility areas. This facility manages the process from raw materials to final product testing and shipping.