We are currently delivering the fit-out of Data Halls 5000 to 8000 at Project Wildcat, a live data centre environment in Denmark. We are working to a robust Statement of Requirements and execution plan that governs every aspect of the build, from enabling works to final commissioning.
Sensori, part of the wider owned Sisk Group of Companies is carrying out all Mechanical and Electrical (M&E) works. This will provide the client with a turnkey service ensuring that this project can be fast tracked through installation, commissioning, and handover with our integrated service approach.
Our team has installed temporary accommodation, drainage, fencing, and power.We have completed detailed dilapidation and as-built surveys to ensure seamless integration with existing infrastructure.
The internal fit-out is currently progressing across all halls. The fit-out includes mechanical and electrical plant installation, internal walls, ceilings and doors, IT infrastructure and electrical plantroom completion.
Externally, we are installing secondary steelwork and louvres into existing cladding and maintaining weather-tight conditions throughout. We have implemented timber protection and spark testing protocols to safeguard the roof membrane and reassure the client of zero damage.